Power & Utilities · 2024

Transmission Substation Modernization

A 345 kV substation rebuilt one bay at a time, with the grid never losing it.

Owner
Confidential
Location
U.S.
Market
Power & Utilities
Delivery
EPC
Scale
345 kV
Completed
2024
The brief

A transmission substation rebuilt bay by bay with no unplanned outage to the grid.

This substation is a key node on the transmission grid, and it had to stay in service while almost all of its equipment was replaced. Outage windows were short, booked months ahead with the grid operator, and could be cancelled on short notice if the system got stressed. Crews worked a few feet from energized equipment every day.

How we built it

The approach.

  1. 01

    Outages planned like launches

    Every bay outage had a switching plan, a minute-by-minute schedule and a rollback plan agreed with system operators.

  2. 02

    Foundations next to live bus

    New foundations and conduit went in with strict approach distances, spotters and a daily energized-work briefing.

  3. 03

    Relays tested twice

    Protection and control panels were tested in the shop and again in place before any bay was energized.

  4. 04

    Bay by bay

    Each rebuilt bay was energized and proven before the next outage began, so the substation was never more than one bay down.

The outcome.

345 kVTransmission voltage
0Unplanned outages
100%Relays tested before energizing
On dateFinal bay energized

“The grid gave us windows, not weeks. We showed up to every one of them ready to finish.”

Project manager, MarkWester
Power & Utilities